Jonkers

Joined: 03 May 2007
Posts: 18
 
 
PostPosted: Tue Mar 24, 2009 12:47 pm    Post subject: RT2 Owners Reply with quote

Has anyone who is buying on RT2 completed yet? Or at least had any communication from PL? On the last update we had it was due to be finished this month?
View user's profile Send private message
Back to top
 

 
Jonkers

Joined: 03 May 2007
Posts: 18
 
 
PostPosted: Tue Oct 06, 2009 10:26 pm    Post subject: Reply with quote

Are there any RT2 purchasers on this forum who can comment on the progress of this development please?
View user's profile Send private message
Back to top
 

 
lightfinger

Joined: 20 Oct 2009
Posts: 2
Location: paris
 
 
PostPosted: Tue Oct 20, 2009 12:00 pm    Post subject: Reply with quote

I'm myself an owner of RT2. I'm trying to get some feedback on the status from PL but without success.
I wonder also about the content of the agreement between Best Western and Property Logic, as I don't see how Best Western will "manage" without an agreement with the owners.
As somebody any news?
View user's profile Send private message
Back to top
 

 
Mark76

Joined: 09 Sep 2008
Posts: 5
 
 
PostPosted: Fri Oct 23, 2009 1:14 pm    Post subject: RT2 Owner Reply with quote

I am also worried at the lack of news coming from the developers! Suzanne was to come back with news on a meeting with Sean at PL but we are still waiting for news?
Can anybody help?
View user's profile Send private message
Back to top
 

 
lightfinger

Joined: 20 Oct 2009
Posts: 2
Location: paris
 
 
PostPosted: Fri Oct 23, 2009 2:53 pm    Post subject: Update on RT2 Reply with quote

I had a long telephone discussion with Sean Cusak.

In short, Property Logic slowed down works in 2008 because:
- they were expecting their british clients to face some payment problems (fall of British pound) if PL was to deliver quickly
- they faced problems with banks, unable to release money on previously agreed borrowings (due to credit crunch)
- the infrastrucures of Saidia are also late and PL didn't want to deliver a resort with little facilities around

RT2 is among the most advanced LJDF properties and should be delivered in March/April 2010. Works are supposed to have resumed but at a slow pace. Can anybody confirm that?

Best Western is already on site, recruiting, training and putting things in place for proper management.

LJDF owners should be contacted to have an individual update on the status of works.
View user's profile Send private message
Back to top
 

Display posts from previous:   
Page 1 of 1 All times are GMT + 2 Hours

 
Post new topic   Reply to topic    saidiaproperty Forum Index -> Le Jardin de Fleur Owners (LJDF)
 
 

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum
 



SmoothBlue phpBB Template by SkaidonDesigns
Powered by phpBB © 2001, 2002 phpBB Group

A phpBB Template by SkaidonDesigns   Back to Top
 
 

Abuse - Report Abuse
Powered by forumup.co.uk free forum, create your free forum!
Created by Raulken of Hyarbor S.r.l.
TOS & Privacy.

Page generation time: 0.034